- Involved in the construction, testing and commissioning for the new 1729 MW Cogeneration Power Plant (SGT5-8000H Gas Turbine Generator and Siemens Steam Turbine Generators.- Manage the Independent Engineer certification as the PPA and Grid Codes requirements.- Ensure the Test & Commissioning Procedures as per the PPA and Grid Codes requirements.- Manage the Operation and Maintenance Team setting up activities such as prepared the procedures for the O&M Team readiness.- Interfacing / Liaison activities with TNB, Energy Commission and others stakeholders for the PTL Transmission Line project (54km Overhead Line Project – Interconnection to the Malaysian Grid) and also for the Pengerang Co-Generation Project.- Interfacing / Liaison activities with the other main PETRONAS RAPID steam & electrical power off-takers.- Review the Steam/Power Sales Purchase Agreement with the Pengerang Integrated Complex customers.- Power Purchase Agreement review and manage the Inter-Operation-Manual (IOM) development with the TNB off-takers.- Manage the Operation Readiness activities in order to take over the Cogen Plant after COD.- Manage the Central Engineering And Maintenance team which supporting the 1729MW Pengerang Cogen Plant (PCP), PAMER, Raw Water Treatment Plant, Sludge Treatment Plant, Effluent Treatment Plant, Cooling Water Plants for Refinery and Crackers Units, Petrochemical Plant C4 Isononanol Plant, Solid Product Warehouse, Solid Product Export Terminal and Jetty- Manage the major maintenance planning such as the Turnaround activities and major maintenance.- Manage the Maintenance Planning and Services for the facilities.- Manage the Engineering Modifications and Plant Upgrading projects.